Mechanical EngineeringVery hard
The critical path of a project has three activities with (a, m, b) times of (2, 3, 8), (4, 5, 10), (3, 6, 9) days. The Z-value for completing the project within 17 days is
- A. 0.56
- B. 1.92
- C. 0.96
- D. 1.20
Correct answer: C. 0.96
Te = Σte = 15.33 days; σ² = Σ[(b − a)/6]² = 3.000; Z = (T − Te)/σ = 0.96.
Practise more Manufacturing, Industrial Engineering & Materials (Mechanical) questionsManufacturing, Industrial Engineering & Materials (Mechanical): notes and key points
More Manufacturing, Industrial Engineering & Materials (Mechanical) questions
- A network has activity A (3 days) followed by two parallel activities B (5 days) and C (4 days), both followed by D (2 days). The minimum…
- A network has activity A (3 days) followed by two parallel activities B (5 days) and C (9 days), both followed by D (3 days). The minimum…
- A product needs a total work content of 60 min. The line must make 40 units in an available time of 450 min. Taking the theoretical…
- A product needs a total work content of 36 min. The line must make 60 units in an available time of 480 min. Taking the theoretical…
- A plain-carbon steel contains 0.2% carbon. At room temperature, treating ferrite as carbon-free, the fraction of pearlite (0.77% C) in the…
- In a tensile test, the engineering stress is 350 MPa at an engineering strain of 0.1 during uniform deformation. The true stress is