The critical path of a project has three activities with (a, m, b) times of (2, 3, 8), (4, 5, 10), (3, 6, 9) days. The Z-value for completing the project within 17 days is

  1. A. 0.56
  2. B. 1.92
  3. C. 0.96
  4. D. 1.20

Correct answer: C. 0.96

Te = Σte = 15.33 days; σ² = Σ[(b − a)/6]² = 3.000; Z = (T − Te)/σ = 0.96.