A network has activity A (3 days) followed by two parallel activities B (5 days) and C (4 days), both followed by D (2 days). The minimum project duration is
- A. 5 days
- B. 9 days
- C. 10 days
- D. 14 days
Correct answer: C. 10 days
Paths: A-B-D = 10, A-C-D = 9; critical path = 10 days; float of C = 1 days.
Practise more Manufacturing, Industrial Engineering & Materials (Mechanical) questionsManufacturing, Industrial Engineering & Materials (Mechanical): notes and key points
More Manufacturing, Industrial Engineering & Materials (Mechanical) questions
- A network has activity A (3 days) followed by two parallel activities B (5 days) and C (9 days), both followed by D (3 days). The minimum…
- A product needs a total work content of 60 min. The line must make 40 units in an available time of 450 min. Taking the theoretical…
- A product needs a total work content of 36 min. The line must make 60 units in an available time of 480 min. Taking the theoretical…
- A plain-carbon steel contains 0.2% carbon. At room temperature, treating ferrite as carbon-free, the fraction of pearlite (0.77% C) in the…
- In a tensile test, the engineering stress is 350 MPa at an engineering strain of 0.1 during uniform deformation. The true stress is
- In a tensile test, the engineering stress is 450 MPa at an engineering strain of 0.15 during uniform deformation. The true stress is