Mechanical EngineeringHard

A network has activity A (3 days) followed by two parallel activities B (5 days) and C (4 days), both followed by D (2 days). The minimum project duration is

  1. A. 5 days
  2. B. 9 days
  3. C. 10 days
  4. D. 14 days

Correct answer: C. 10 days

Paths: A-B-D = 10, A-C-D = 9; critical path = 10 days; float of C = 1 days.