Mechanical EngineeringHard
A PERT activity has optimistic time 2 days, most likely time 4 days and pessimistic time 6 days. The expected duration is
- A. 3.20 days
- B. 6.00 days
- C. 5.00 days
- D. 4.00 days
Correct answer: D. 4.00 days
te = (a + 4m + b)/6 = (2 + 16 + 6)/6 = 4.00 days.
Practise more Manufacturing, Industrial Engineering & Materials (Mechanical) questionsManufacturing, Industrial Engineering & Materials (Mechanical): notes and key points
More Manufacturing, Industrial Engineering & Materials (Mechanical) questions
- The critical path of a project has three activities with (a, m, b) times of (2, 3, 8), (4, 5, 10), (3, 6, 9) days. The Z-value for…
- A network has activity A (3 days) followed by two parallel activities B (5 days) and C (4 days), both followed by D (2 days). The minimum…
- A network has activity A (3 days) followed by two parallel activities B (5 days) and C (9 days), both followed by D (3 days). The minimum…
- A product needs a total work content of 60 min. The line must make 40 units in an available time of 450 min. Taking the theoretical…
- A product needs a total work content of 36 min. The line must make 60 units in an available time of 480 min. Taking the theoretical…
- A plain-carbon steel contains 0.2% carbon. At room temperature, treating ferrite as carbon-free, the fraction of pearlite (0.77% C) in the…