A 25 mm hole has limits +25 µm / 0 and the mating shaft has deviations -20 µm (upper) and -45 µm (lower) from basic size. The maximum clearance is
- A. 50 µm
- B. 88 µm
- C. 45 µm
- D. 70 µm
Correct answer: D. 70 µm
Max clearance = largest hole − smallest shaft = (+25) − (-45) = 70 µm; min clearance = 0 − (-20) = 20 µm.
Practise more Manufacturing, Industrial Engineering & Materials (Mechanical) questionsManufacturing, Industrial Engineering & Materials (Mechanical): notes and key points
More Manufacturing, Industrial Engineering & Materials (Mechanical) questions
- Four parts of ±0.02, ±0.05, ±0.05 and ±0.05 mm tolerance are stacked end to end. Using the statistical (root-sum-square) method the…
- Using i = 0.45∛D + 0.001D (µm, D = geometric mean of the diameter step in mm) and IT6 = 10i, the standard tolerance for the 80–120 mm…
- For annual demand 2400 units, ordering cost ₹300 per order and holding cost ₹8/unit/year, the minimum total annual ordering plus holding…
- Using exponential smoothing with α = 0.3, the forecast for period 1 was 100. Actual demands were 90 (period 1) and 100 (period 2). The…
- Using exponential smoothing with α = 0.3, the forecast for period 1 was 150. Actual demands were 130 (period 1) and 140 (period 2). The…
- A product sells at ₹50 per unit with a variable cost of ₹40 per unit and fixed costs of ₹60000. The number of units to earn a profit of…