A contract priced at ₹50 lakh is accounted for over time using the cost-to-cost input method. Costs to date are ₹18 lakh and further costs to complete are estimated at ₹12 lakh. How much profit is recognised to date?
- A. ₹20 lakh
- B. ₹30 lakh
- C. ₹12 lakh
- D. ₹8 lakh
Correct answer: C. ₹12 lakh
Progress = 18 ÷ 30 = 60%. Revenue to date = 60% × 50 = ₹30 lakh; profit = 30 − 18 = ₹12 lakh (60% of the expected ₹20 lakh). ₹30 lakh is the revenue, not the profit; ₹8 lakh applies the 40% still to be done.
Practise more Financial & Cost Accounting questionsFinancial & Cost Accounting: notes and key points
More Financial & Cost Accounting questions
- A fixed-price contract for ₹40 lakh has incurred costs of ₹25 lakh and needs a further ₹20 lakh to complete. It is 25/45 complete. How…
- Match each overhead with its usual basis of apportionment. (a) Factory rent (b) Canteen expenses (c) Power for machines (d) Insurance of…
- Kaizen costing aims at:
- A bottleneck machine has 10,000 hours a year and total factory costs (all costs other than materials) are ₹6,00,000. Product B sells at…
- 5,000 debentures of ₹100, redeemable at a 10% premium, are redeemed by converting them into equity shares of ₹10 each issued at ₹12.50…
- In a consignment, the periodical statement showing the goods sold, the gross proceeds, the expenses incurred and the commission deducted…