Project A has cash flows (−100, +60, +60) and project B (−100, 0, +130) over years 0–2. At what discount rate do the two NPVs become equal (the crossover rate)?

  1. A. 13.07%
  2. B. 16.67%
  3. C. 14.02%
  4. D. 13.54%

Correct answer: B. 16.67%

Equate NPVs by finding the IRR of the difference (0, +60, −70): 60/(1+r) = 70/(1+r)², so 1 + r = 70/60 and r = 16.67%. Below it B (later, bigger cash) has the higher NPV; above it A does.