Management & CommerceHardProject analyst · MBA placement

A project has a budget at completion of ₹100 lakh. At the end of month 6 the planned value is ₹50 lakh, the earned value ₹40 lakh and the actual cost ₹50 lakh. If the current cost performance continues, what is the estimate at completion (EAC)?

  1. A. ₹110 lakh
  2. B. ₹100 lakh
  3. C. ₹125 lakh
  4. D. ₹80 lakh

Correct answer: C. ₹125 lakh

CPI = EV/AC = 40/50 = 0.8, so EAC = BAC/CPI = 100/0.8 = ₹125 lakh. ₹110 lakh (AC + remaining budget) assumes future work will be done at budget rates, which contradicts 'current performance continues'.

More Operations, Supply Chain & Business Analytics questions

Exams that ask this topic