A project has a budget at completion of ₹100 lakh. At the end of month 6 the planned value is ₹50 lakh, the earned value ₹40 lakh and the actual cost ₹50 lakh. If the current cost performance continues, what is the estimate at completion (EAC)?
- A. ₹110 lakh
- B. ₹100 lakh
- C. ₹125 lakh
- D. ₹80 lakh
Correct answer: C. ₹125 lakh
CPI = EV/AC = 40/50 = 0.8, so EAC = BAC/CPI = 100/0.8 = ₹125 lakh. ₹110 lakh (AC + remaining budget) assumes future work will be done at budget rates, which contradicts 'current performance continues'.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A project has a single critical path of 20 days and no other path longer than 12 days. Indirect costs are ₹5,000 a day. Activities on the…
- Maximise Z = 4x + 3y subject to 2x + y ≤ 20, x + 3y ≤ 30, x ≤ 8, x, y ≥ 0. What is the optimal value of Z, and which constraint is not…
- Maximise Z = 4x + 5y subject to x + y ≤ 8, x + 3y ≤ 18, x, y ≥ 0. The optimum is x = 3, y = 5. Keeping everything else fixed, over what…
- A refinery makes products A (x litres) and B (y litres). Management insists that A must be at least 30% of total output. Which linear…
- In the optimal LP solution of a product-mix problem, product T is not produced and its reduced cost is −₹6 per unit. What does this mean?
- An LP for the number of trucks to buy gives x = 3.6, y = 2.4 at the optimum. Which statement about simply rounding to x = 4, y = 2 is…