Management & CommerceVery hardOps MT · MBA placement
Product X (lead time 1 week) needs 2 units of Y; Y (lead time 2 weeks) needs 3 units of Z; Z has a lead time of 1 week. 100 units of X are due in week 8. There are 50 units of Y on hand and nothing else. When must an order for Z be released, and for how many units?
- A. 600 units in week 4
- B. 450 units in week 4
- C. 450 units in week 5
- D. 600 units in week 6
Correct answer: B. 450 units in week 4
X is released in week 7, so Y's gross need is 200 in week 7; net of 50 on hand it is 150, released in week 5. Z's gross need is 3 × 150 = 450 in week 5, released one week earlier in week 4. Ignoring Y's stock gives 600.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Four jobs wait at one machine (processing hours; weight = importance): A (4; 1), B (2; 3), C (6; 2), D (3; 3). Using the weighted shortest…
- Seven jobs taking 8, 7, 6, 5, 4, 3 and 2 hours are to be run on three identical parallel machines. Using the longest-processing-time (LPT)…
- A machine has a mean time between failures of 400 hours and a mean time to repair of 20 hours. What is its steady-state availability?
- A pump fails at random (constant failure rate) with a mean time between failures of 400 hours. What is the probability that it runs a…
- A subscriber yields a margin of ₹600 a year, paid at the end of each year he stays. The annual retention rate is 80% and the discount rate…
- Acquiring a customer costs ₹3,000. Each customer pays ₹500 a month at a 60% gross margin and is retained throughout. Ignoring discounting…