In simple exponential smoothing with α = 0.3, how much weight does the current forecast give to the actual demand of 3 periods before the most recent one (i.e. the 4th most recent observation)?

  1. A. About 0.0720
  2. B. About 0.027
  3. C. About 0.1029
  4. D. About 0.147

Correct answer: C. About 0.1029

The k-th most recent observation (k = 0 for the latest) gets weight α(1 − α)ᵏ. For k = 3: 0.3 × 0.7³ ≈ 0.1029. 0.147 is the weight for k = 2 and 0.0720 for k = 4 (off-by-one in counting back); 0.027 cubes α instead of (1 − α).