Management & CommerceVery hardOps MT · MBA placement

A process holds an average of 600 units of WIP and completes 200 units per 8-hour working day. The value-added work on each unit totals 30 minutes. What is its process cycle efficiency?

  1. A. About 6.25%
  2. B. About 2.08%
  3. C. About 0.69%
  4. D. About 33.3%

Correct answer: B. About 2.08%

Little's law: lead time = WIP ÷ throughput = 600/200 = 3 working days = 1,440 minutes. PCE = 30/1,440 ≈ 2.08%. Using one day as the lead time gives 6.25%; using 24-hour days gives 0.69%.