A process holds an average of 600 units of WIP and completes 200 units per 8-hour working day. The value-added work on each unit totals 30 minutes. What is its process cycle efficiency?
- A. About 6.25%
- B. About 2.08%
- C. About 0.69%
- D. About 33.3%
Correct answer: B. About 2.08%
Little's law: lead time = WIP ÷ throughput = 600/200 = 3 working days = 1,440 minutes. PCE = 30/1,440 ≈ 2.08%. Using one day as the lead time gives 6.25%; using 24-hour days gives 0.69%.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A machine has a mean processing time of 4 minutes and runs at 90% utilisation. The squared coefficient of variation is 1 for inter-arrival…
- Activities A (4 days) and B (6 days) can start at once and run in parallel, and C (3 days) can start only when both are done. A and B each…
- A firm has ₹10 crore to invest and four indivisible projects (cost; NPV, ₹ crore): P1 (5; 8), P2 (4; 6), P3 (3; 5), P4 (6; 9). Which…
- A decision-maker's utility for wealth x (₹ lakh) is u(x) = √x. She is offered a venture paying ₹100 lakh with probability 0.5 and nothing…
- In a survey of 400 customers, 120 say they would pay for express delivery. What is the 95% confidence interval for the true proportion?
- In acceptance sampling, a good lot (at the acceptable quality level) is rejected by the sampling plan. What kind of error is this, and who…