Activity A takes 5 days. Activity B takes 4 days and has two links with A: it can start no earlier than 2 days after A starts (start-to-start lag 2), and it can finish no earlier than 1 day after A finishes (finish-to-finish lag 1). With no other activities, what is the shortest project duration?

  1. A. 11 days
  2. B. 6 days
  3. C. 9 days
  4. D. 7 days

Correct answer: B. 6 days

B may start on day 2, which would end it on day 6. The finish-to-finish link needs B to end no earlier than 5 + 1 = 6. Both are met with B from day 2 to day 6, so the project takes 6 days. Treating the links as finish-to-start gives 9 or more.