Activity A takes 5 days. Activity B takes 4 days and has two links with A: it can start no earlier than 2 days after A starts (start-to-start lag 2), and it can finish no earlier than 1 day after A finishes (finish-to-finish lag 1). With no other activities, what is the shortest project duration?
- A. 11 days
- B. 6 days
- C. 9 days
- D. 7 days
Correct answer: B. 6 days
B may start on day 2, which would end it on day 6. The finish-to-finish link needs B to end no earlier than 5 + 1 = 6. Both are met with B from day 2 to day 6, so the project takes 6 days. Treating the links as finish-to-start gives 9 or more.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- At a project review, earned value is ₹40 lakh, planned value ₹50 lakh and actual cost ₹35 lakh. Which statement is correct?
- A maximisation LP has 3 '≤' constraints and 4 decision variables. After adding slack variables, how many variables are basic in any basic…
- A resource's shadow price in an LP is ₹12 per hour, valid for right-hand-side values between 80 and 140 hours; the current availability is…
- For a decision, the expected value of perfect information is ₹18 lakh and the expected value of the sample information from a proposed…
- A supplier's lead time is uniformly distributed between 4 and 10 days. What is the probability that a given order takes more than 8 days…
- What do =MROUND(37, 5), =CEILING(37, 5) and =FLOOR(37, 5) return in Excel?