A team compares two suppliers' processes for the same part: Process P has Cp = 1.8 and Cpk = 0.9; Process Q has Cp = 1.3 and Cpk = 1.25. Which statement is correct?
- A. Q has fewer defects now; re-centring alone could make P far better
- B. P is better now, because its higher Cp means a much narrower spread
- C. Both are equally capable, because both Cp values are above 1
- D. Q is better now, and P cannot improve without reducing its variation
Correct answer: A. Q has fewer defects now; re-centring alone could make P far better
Cpk reflects actual performance including centring: P's mean is far off target (Cpk 0.9), so it makes more defects than Q (Cpk 1.25). P's high Cp shows low spread, so centring alone would lift its Cpk towards 1.8.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- An item is ordered 20 times a year. Holding cost is ₹8 per unit per year and each unit short costs ₹30. Expected units short per cycle for…
- A single-server desk (M/M/1) has λ = 8 per hour and μ = 10 per hour. In an M/M/1 queue, time in system is exponential with mean 1/(μ − λ)…
- A clinic with 3 doctors receives 12 patients an hour. On average there are 6 patients in the clinic, of whom 4 are waiting (not with a…
- For an assembly line, which statement about the feasible range of cycle time is correct?
- A product's Q4 sales were 600 units, and its multiplicative seasonal index for Q4 is 1.25. What are its deseasonalised Q4 sales?
- Forecast errors are defined as actual − forecast. Over 12 months the mean forecast error is +35 units and the tracking signal is +5.2…