A part is made in lots of 1,200 at a production rate of 100 per day, while it is used at 40 per day throughout the year. In each production cycle, for how many days is the machine not making this part?
- A. 12 days
- B. 30 days
- C. 720 days
- D. 18 days
Correct answer: D. 18 days
Run time per lot = 1,200/100 = 12 days; the lot lasts 1,200/40 = 30 days; so the machine is free for other work for 30 − 12 = 18 days per cycle. (The maximum stock is 1,200 × (1 − 40/100) = 720 units, not a number of days.)
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Three stations in series each take 1 minute per unit. A batch of 50 units moves from station to station only when the whole batch is done…
- An audit of 2,000 invoices finds 96 errors. Each invoice has 8 distinct fields where an error can occur. What is the DPMO?
- Match each situation with the most suitable control chart. 1. Number of scratches per car body (same body size each time) 2. Defects per…
- Two paths are both critical at 15 days: A → B and A → C (A is shared). Crash costs per day: A ₹5,000, B ₹3,000, C ₹3,500, and each can be…
- At the end of the simplex method (Big-M or Phase I), an artificial variable is still in the basis at a positive value. What does this…
- In the optimal simplex tableau of a maximisation problem, a non-basic decision variable has a reduced cost (net evaluation) of exactly…