A part is made in lots of 1,200 at a production rate of 100 per day, while it is used at 40 per day throughout the year. In each production cycle, for how many days is the machine not making this part?

  1. A. 12 days
  2. B. 30 days
  3. C. 720 days
  4. D. 18 days

Correct answer: D. 18 days

Run time per lot = 1,200/100 = 12 days; the lot lasts 1,200/40 = 30 days; so the machine is free for other work for 30 − 12 = 18 days per cycle. (The maximum stock is 1,200 × (1 − 40/100) = 720 units, not a number of days.)