Three stations in series each take 1 minute per unit. A batch of 50 units moves from station to station only when the whole batch is done. With one-piece flow instead, units move one at a time. When does the first unit of the order finish in each case?
- A. Batch: after 52 minutes; one-piece flow: after 3 minutes
- B. Batch: after 150 minutes; one-piece flow: after 52 minutes
- C. Batch: after 150 minutes; one-piece flow: after 3 minutes
- D. Both after 150 minutes, because total work is the same
Correct answer: C. Batch: after 150 minutes; one-piece flow: after 3 minutes
With transfer batches of 50, no unit leaves station 3 until all three stations have each spent 50 minutes: 150 minutes. One-piece flow finishes the first unit in 3 minutes and the whole order in 52 minutes – the same work, much shorter lead time.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- An audit of 2,000 invoices finds 96 errors. Each invoice has 8 distinct fields where an error can occur. What is the DPMO?
- Match each situation with the most suitable control chart. 1. Number of scratches per car body (same body size each time) 2. Defects per…
- Two paths are both critical at 15 days: A → B and A → C (A is shared). Crash costs per day: A ₹5,000, B ₹3,000, C ₹3,500, and each can be…
- At the end of the simplex method (Big-M or Phase I), an artificial variable is still in the basis at a positive value. What does this…
- In the optimal simplex tableau of a maximisation problem, a non-basic decision variable has a reduced cost (net evaluation) of exactly…
- A transportation problem has 3 sources and 4 destinations. Written as a linear programme, how many decision variables and how many…