Demand grows by exactly 10 units every period. Simple exponential smoothing with α = 0.2 has been used for a long time. Once things settle, by how much does each period's forecast fall short of that period's actual demand?

  1. A. 40 units
  2. B. 10 units
  3. C. 8 units
  4. D. 50 units

Correct answer: D. 50 units

On a linear trend, simple smoothing settles into a steady lag: the error (actual − forecast) equals trend/α = 10/0.2 = 50. Lower α means a smoother but more lagging forecast, which is why trend-adjusted (Holt) smoothing exists.