Management & CommerceVery hardOps MT · MBA placement
Demand grows by exactly 10 units every period. Simple exponential smoothing with α = 0.2 has been used for a long time. Once things settle, by how much does each period's forecast fall short of that period's actual demand?
- A. 40 units
- B. 10 units
- C. 8 units
- D. 50 units
Correct answer: D. 50 units
On a linear trend, simple smoothing settles into a steady lag: the error (actual − forecast) equals trend/α = 10/0.2 = 50. Lower α means a smoother but more lagging forecast, which is why trend-adjusted (Holt) smoothing exists.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A process has Cp = 2.0 (spec limits ±6σ) and its mean then drifts by 1.5σ, as assumed in Six Sigma tables. What is its Cpk?
- A p-chart is used for a process with p̄ = 0.05. What is the smallest sample size that gives a positive lower control limit with 3-sigma…
- A project's critical path is 120 days long, but the contract requires completion in 110 days. When CPM is computed backward from the…
- Three activities have PERT estimates (optimistic, most likely, pessimistic) in days: P (2, 5, 14), Q (4, 6, 8), R (1, 8, 9). Which…
- An LP has the constraints x + y ≤ 10, x ≤ 6 and 2x + 2y ≤ 30, with x, y ≥ 0. Which constraint is redundant?
- Three workers must be assigned to four jobs, one job each at most, to minimise cost. How should the Hungarian method be applied?