Demand requires a takt time of 45 seconds, but the bottleneck station's work content is 50 seconds and cannot be split. What is the minimum fix that lets the line meet takt?

  1. A. Duplicate the bottleneck station so two operators work in parallel
  2. B. Speed up the non-bottleneck stations to recover the 5-second gap
  3. C. Increase the batch size so the bottleneck runs longer between setups
  4. D. Reduce the takt time to 40 seconds so the line runs faster

Correct answer: A. Duplicate the bottleneck station so two operators work in parallel

An indivisible 50-second task cannot meet a 45-second takt on one station. Two parallel stations give an effective cycle of 25 seconds, which meets takt. Faster non-bottlenecks or bigger batches do not change the bottleneck's rate.