Management & CommerceHardOps MT · MBA placement
Demand requires a takt time of 45 seconds, but the bottleneck station's work content is 50 seconds and cannot be split. What is the minimum fix that lets the line meet takt?
- A. Duplicate the bottleneck station so two operators work in parallel
- B. Speed up the non-bottleneck stations to recover the 5-second gap
- C. Increase the batch size so the bottleneck runs longer between setups
- D. Reduce the takt time to 40 seconds so the line runs faster
Correct answer: A. Duplicate the bottleneck station so two operators work in parallel
An indivisible 50-second task cannot meet a 45-second takt on one station. Two parallel stations give an effective cycle of 25 seconds, which meets takt. Faster non-bottlenecks or bigger batches do not change the bottleneck's rate.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Four jobs wait at one machine (processing days; due day): A (3; 5), B (2; 4), C (4; 12), D (5; 9). What is the maximum lateness under the…
- A control system has three identical sensors, each with reliability 0.9, and it works if at least two of the three work (independent…
- A planner computes the EOQ using an annual demand forecast that turns out to be 50% too high (true demand is two-thirds of the forecast)…
- At a single-server counter (M/M/1) with λ = 6 per hour and μ = 8 per hour, what is the difference between the average number in the system…
- A line's tasks total 40 minutes of work per unit and the cycle time is 6 minutes. Precedence constraints force the planner to use 8…
- What does =DATE(2028,3,1) - DATE(2028,2,1) return in Excel (with the result formatted as a number)?