Management & CommerceModerateOperations · project management · MBA placement
A project manager must cut two weeks from a schedule. She considers starting interior work before all structural approvals are complete, instead of after. What is this technique, and what is its main drawback compared with crashing?
- A. Crashing; it adds resources to critical activities and always raises cost
- B. Resource levelling; it smooths resource use but lengthens the project
- C. Critical chain; it removes task buffers and adds one project buffer
- D. Fast-tracking; overlapping sequential work risks rework, not extra cost
Correct answer: D. Fast-tracking; overlapping sequential work risks rework, not extra cost
Fast-tracking runs sequential activities in parallel, which saves time without extra resources but risks rework if earlier work changes. Crashing adds resources to critical activities at extra cost.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A firm adopting Goldratt's critical chain method strips the safety margin out of each task estimate and instead places one shared buffer…
- A firm wants to lay fibre linking five sites at minimum total cable length. Possible links (km): A–B 4, A–C 3, B–C 2, B–D 5, C–D 7, C–E 8…
- Pipelines (capacity in kilolitres per hour): Source→A 10, Source→B 8, A→B 2, A→Sink 6, B→Sink 9. What is the maximum flow from Source to…
- A van leaves depot D, visits A, B, C and E once each and returns. Distances (km): D–A 30, D–B 19, D–C 18, D–E 17, A–B 15, A–C 22, A–E 23…
- A sales regression has strongly autocorrelated residuals: each month's error tends to have the same sign as the last. What value of the…
- A regression predicts store sales from advertising (₹ lakh) and footfall (thousands). The raw coefficients are 4.0 for advertising and 0.5…