Management & CommerceModerateOperations · project management · MBA placement

A project manager must cut two weeks from a schedule. She considers starting interior work before all structural approvals are complete, instead of after. What is this technique, and what is its main drawback compared with crashing?

  1. A. Crashing; it adds resources to critical activities and always raises cost
  2. B. Resource levelling; it smooths resource use but lengthens the project
  3. C. Critical chain; it removes task buffers and adds one project buffer
  4. D. Fast-tracking; overlapping sequential work risks rework, not extra cost

Correct answer: D. Fast-tracking; overlapping sequential work risks rework, not extra cost

Fast-tracking runs sequential activities in parallel, which saves time without extra resources but risks rework if earlier work changes. Crashing adds resources to critical activities at extra cost.