Management & CommerceEasyOps MT · Supply chain · MBA placement pattern
Which of the following is NOT one of the classic seven wastes of lean production?
- A. Unnecessary motion
- B. Standardised work
- C. Overproduction
- D. Over-processing
Correct answer: B. Standardised work
The seven wastes (TIMWOOD) are transport, inventory, motion, waiting, overproduction, over-processing and defects. Standardised work is a lean tool for removing waste, not a waste.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Twenty samples of size 5 give a grand mean of 50.0 mm and an average range of 4.0 mm. With A2 = 0.577 for n = 5, what is the upper control…
- Twenty-five samples of 200 items each contain 250 defectives in total. What are the 3-sigma control limits of the p-chart?
- A process is monitored with X̄ and R charts (n = 4): X̿ = 25, R̄ = 6.2, A2 = 0.729, D3 = 0, D4 = 2.282. Three new samples are taken: S1 =…
- A shaft's diameter specification is 10.0 ± 0.6 mm. The process mean is 10.2 mm and the standard deviation is 0.15 mm. What is Cpk?
- A part passes through three steps whose first-pass yields are 98%, 95% and 97%. What is the rolled throughput yield?
- A call centre audits 25,000 calls; each call has 5 defect opportunities, and 780 defects are found. Reference values (with the 1.5σ…