A process is monitored with X̄ and R charts (n = 4): X̿ = 25, R̄ = 6.2, A2 = 0.729, D3 = 0, D4 = 2.282. Three new samples are taken: S1 = 27, 30, 24, 33; S2 = 19, 34, 25, 22; S3 = 31, 26, 34, 29. Which samples signal that the process is out of control?
- A. S3 only
- B. S2 and S3 only
- C. S1, S2 and S3
- D. S1 and S3 only
Correct answer: B. S2 and S3 only
X̄ limits = 25 ± 0.729 × 6.2 = 20.48 to 29.52; R limits = 0 to 2.282 × 6.2 = 14.15. S1: mean 28.5, range 9 → in control. S2: mean 25, range 15 → range out. S3: mean 30, range 8 → mean out. Checking only the X̄-chart misses S2.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A shaft's diameter specification is 10.0 ± 0.6 mm. The process mean is 10.2 mm and the standard deviation is 0.15 mm. What is Cpk?
- A part passes through three steps whose first-pass yields are 98%, 95% and 97%. What is the rolled throughput yield?
- A call centre audits 25,000 calls; each call has 5 defect opportunities, and 780 defects are found. Reference values (with the 1.5σ…
- Match each quality tool with its main use. 1. Pareto chart 2. Cause-and-effect (fishbone) diagram 3. Control chart 4. Scatter diagram a…
- Assertion (A): A process can be in statistical control and still produce many units outside specification. Reason (R): Control limits come…
- Which statements are correct? I. Poka-yoke aims to make errors impossible or immediately obvious. II. Kaizen relies mainly on large…