Management & CommerceModerateMBA Placement · Project Analyst
A project has activities A (3 days) and B (2 days), which start at once; C (8 days) follows A; D (2 days) follows B; E (3 days) follows D; F (1 day) follows both C and E. What are the total float and free float of activity B?
- A. Total float 4, free float 4
- B. Total float 0, free float 0
- C. Total float 0, free float 4
- D. Total float 4, free float 0
Correct answer: D. Total float 4, free float 0
The critical path A–C–F is 12 days; B–D–E–F is 8 days, so B has total float 4. But D can start as soon as B ends (day 2), so any delay to B delays D: free float = ES(D) − EF(B) = 0. The 4 days of free float sit on E.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A project has two independent paths that both end the project: A (6 days) then C (5 days), and B (8 days) then D (2 days). Crash costs and…
- A firm moves 36,500 units a year of a ₹2,000 part. Sea freight takes 6 days in transit; air takes 1 day. The buyer owns goods in transit…
- A warehouse ships SKU P at 300 units/day and holds on average 1,200 units of it; SKU Q ships 100 units/day with 1,000 units on hand on…
- A single-server M/M/1 counter has utilisation 0.8. Demand grows so utilisation becomes 0.9 with the same service rate. By what factor does…
- An item has 50 units on hand at the start of week 1. The master schedule has receipts of 100 in week 1 and 100 in week 3. Customer orders…
- Net requirements for four weeks are 60, 40, 100 and 30 units. Setup cost is ₹150 per order and holding cost ₹1.5 per unit per week…