A project has activities A (3 days) and B (2 days), which start at once; C (8 days) follows A; D (2 days) follows B; E (3 days) follows D; F (1 day) follows both C and E. What are the total float and free float of activity B?

  1. A. Total float 4, free float 4
  2. B. Total float 0, free float 0
  3. C. Total float 0, free float 4
  4. D. Total float 4, free float 0

Correct answer: D. Total float 4, free float 0

The critical path A–C–F is 12 days; B–D–E–F is 8 days, so B has total float 4. But D can start as soon as B ends (day 2), so any delay to B delays D: free float = ES(D) − EF(B) = 0. The 4 days of free float sit on E.