Management & CommerceHardMBA Placement · Business Analyst · Excel test
B2:B9 hold 40, 55, 70, 85, 100, 25, 90 and 15. What do P: =COUNTIF(B2:B9, ">"&AVERAGE(B2:B9)) and Q: =COUNTIF(B2:B9, ">AVERAGE(B2:B9)") return?
- A. 4 and 4
- B. 5 and 0
- C. 4 and 0
- D. 4 and #VALUE!
Correct answer: C. 4 and 0
P builds the criterion ">60" from the average (480/8 = 60) and counts 70, 85, 100, 90: 4. In Q the function is inside quotes, so it is the literal text 'AVERAGE(B2:B9)', which no number exceeds in COUNTIF's sense: 0, with no error.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A data scientist tunes a model over 3 values of one parameter and 4 of another, scoring each combination with 5-fold cross-validation, and…
- Annual demand is 12,000 units, ordering cost is ₹300 per order and holding cost is 20% of unit price. The supplier charges ₹50 a unit for…
- Customers arrive at a single-server counter at 8 per hour and the server handles 10 per hour (M/M/1). What is the average time a customer…
- A project's critical path has three activities with (optimistic, most likely, pessimistic) durations in days: (6, 9, 12), (4, 10, 16) and…
- A process has mean 50, standard deviation 2, USL 56 and LSL 40. What is its Cpk?
- Maximise 40x + 30y subject to x + y <= 12 (labour hours), 2x + y <= 16 (machine hours), x, y >= 0. What is the shadow price per extra…