Management & CommerceHardMBA Placement · Operations · Six Sigma
A process has mean 50, standard deviation 2, USL 56 and LSL 40. What is its Cpk?
- A. 1.33
- B. 1.00
- C. 1.67
- D. 3.00
Correct answer: B. 1.00
Cpu = (56 - 50)/(3 x 2) = 1.00 and Cpl = (50 - 40)/6 = 1.67; Cpk is the smaller, 1.00. Cp = 16/12 = 1.33 ignores centring; 3.00 is the Z-score to the nearer limit.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Maximise 40x + 30y subject to x + y <= 12 (labour hours), 2x + y <= 16 (machine hours), x, y >= 0. What is the shadow price per extra…
- Annual demand is 12,000 units, ordering cost is ₹300 per order and holding cost is 20% of the unit price per year. The supplier charges…
- Customers arrive at a service counter at 8 per hour (Poisson) and are served at 10 per hour (exponential), a single-server M/M/1 queue…
- A firm maximises profit 40x + 30y subject to 2x + y ≤ 100 (machine hours), x + y ≤ 80 (labour hours) and x ≤ 40. At the optimum, the…
- A forecaster uses simple exponential smoothing with α = 0.3 and an initial forecast of 100 for period 1. The actual demands in periods 1…
- A project's critical path A → B → D has three-point time estimates (optimistic, most likely, pessimistic, in weeks) of A (2, 4, 6), B (3…