A firm maximises profit 40x + 30y subject to 2x + y ≤ 100 (machine hours), x + y ≤ 80 (labour hours) and x ≤ 40. At the optimum, the shadow price of one more machine hour is:
- A. ₹20
- B. ₹30
- C. ₹40
- D. ₹10
Correct answer: D. ₹10
The optimum is x = 20, y = 60 (profit 2,600) at the intersection of the first two constraints. Solving the dual 2u + v = 40, u + v = 30 gives u = 10 (machine hours) and v = 20 (labour hours). One more machine hour moves the vertex to (21, 59), raising profit by 10. The value 20 is the shadow price of labour.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A forecaster uses simple exponential smoothing with α = 0.3 and an initial forecast of 100 for period 1. The actual demands in periods 1…
- A project's critical path A → B → D has three-point time estimates (optimistic, most likely, pessimistic, in weeks) of A (2, 4, 6), B (3…
- Daily demand averages 100 units with a standard deviation of 20; the lead time averages 9 days with a standard deviation of 2 days…
- Annual demand is 12,000 units, ordering cost ₹300 per order and holding cost 20% of unit price per year. The supplier charges ₹50 per unit…
- Daily demand has mean 100 and standard deviation 20. The supplier's lead time has mean 9 days and standard deviation 2 days (independent…
- Customers arrive at 8 per hour (Poisson) at a service desk with two servers, each serving at 5 customers per hour (exponential). The…