A project's critical path A → B → D has three-point time estimates (optimistic, most likely, pessimistic, in weeks) of A (2, 4, 6), B (3, 5, 13) and D (4, 6, 8); the non-critical path through C is clearly shorter. Take Φ(1.04) = 0.851. The probability that the project finishes within 18 weeks is closest to:

  1. A. 0.71
  2. B. 0.85
  3. C. 0.97
  4. D. 0.50

Correct answer: B. 0.85

Expected times are 4, 6 and 6, so the mean is 16 weeks. Variances are (4/6)², (10/6)² and (4/6)², totalling 3.67, so σ = 1.915 and Z = (18 − 16)/1.915 = 1.04, giving 0.851. Dividing by the variance instead of σ gives Z = 0.55 and 0.71.