A project's critical path A → B → D has three-point time estimates (optimistic, most likely, pessimistic, in weeks) of A (2, 4, 6), B (3, 5, 13) and D (4, 6, 8); the non-critical path through C is clearly shorter. Take Φ(1.04) = 0.851. The probability that the project finishes within 18 weeks is closest to:
- A. 0.71
- B. 0.85
- C. 0.97
- D. 0.50
Correct answer: B. 0.85
Expected times are 4, 6 and 6, so the mean is 16 weeks. Variances are (4/6)², (10/6)² and (4/6)², totalling 3.67, so σ = 1.915 and Z = (18 − 16)/1.915 = 1.04, giving 0.851. Dividing by the variance instead of σ gives Z = 0.55 and 0.71.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Daily demand averages 100 units with a standard deviation of 20; the lead time averages 9 days with a standard deviation of 2 days…
- Annual demand is 12,000 units, ordering cost ₹300 per order and holding cost 20% of unit price per year. The supplier charges ₹50 per unit…
- Daily demand has mean 100 and standard deviation 20. The supplier's lead time has mean 9 days and standard deviation 2 days (independent…
- Customers arrive at 8 per hour (Poisson) at a service desk with two servers, each serving at 5 customers per hour (exponential). The…
- A line must produce 480 units in an 8-hour shift. The total work content of all tasks is 5.4 minutes per unit. With perfect balancing, the…
- A firm maximises 40x + 30y subject to machine hours 2x + y ≤ 100, labour hours x + y ≤ 80 and x ≤ 40. At the optimum, the shadow price…