Management & CommerceHardMBA Placement · Operations · Analytics
A line must produce 480 units in an 8-hour shift. The total work content of all tasks is 5.4 minutes per unit. With perfect balancing, the minimum number of stations and the resulting line efficiency are
- A. 5 stations, 108%
- B. 6 stations, 90%
- C. 6 stations, 100%
- D. 7 stations, 77%
Correct answer: B. 6 stations, 90%
Takt time = 480 min/480 units = 1.0 min, so stations ≥ 5.4/1.0 = 5.4 → 6. Efficiency = 5.4/(6 × 1.0) = 90%. Five stations would need more than the takt time at some station.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A firm maximises 40x + 30y subject to machine hours 2x + y ≤ 100, labour hours x + y ≤ 80 and x ≤ 40. At the optimum, the shadow price…
- Four jobs must be assigned to four machines, one each. The cost matrix (rows jobs 1-4, columns machines 1-4) is: job 1: 14, 9, 17, 12; job…
- Demand forecast errors (actual − forecast) over five periods are +5, −3, +6, +8 and +4. The tracking signal after five periods is closest to
- Project network: A (4 days) and B (6) start together; C (5) follows A; D (3) follows B; E (4) follows both C and D. Crash limits and cost…
- A project has four sequential activities with (optimistic, most likely, pessimistic) times of (2, 5, 8), (4, 6, 14), (1, 3, 5) and (6, 9…
- Annual demand is 24,000 units over 300 working days (80 per day), ordering/setup cost ₹400, holding cost ₹10 per unit per year, and the…