Demand forecast errors (actual − forecast) over five periods are +5, −3, +6, +8 and +4. The tracking signal after five periods is closest to

  1. A. 3.85
  2. B. 0.77
  3. C. 5.20
  4. D. 4.00

Correct answer: A. 3.85

The running sum of forecast errors is 20 and MAD = (5 + 3 + 6 + 8 + 4)/5 = 5.2, so the tracking signal = 20/5.2 = 3.85. A value this far above ±3 or 4 flags bias in the forecast.