Demand forecast errors (actual − forecast) over five periods are +5, −3, +6, +8 and +4. The tracking signal after five periods is closest to
- A. 3.85
- B. 0.77
- C. 5.20
- D. 4.00
Correct answer: A. 3.85
The running sum of forecast errors is 20 and MAD = (5 + 3 + 6 + 8 + 4)/5 = 5.2, so the tracking signal = 20/5.2 = 3.85. A value this far above ±3 or 4 flags bias in the forecast.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Project network: A (4 days) and B (6) start together; C (5) follows A; D (3) follows B; E (4) follows both C and D. Crash limits and cost…
- A project has four sequential activities with (optimistic, most likely, pessimistic) times of (2, 5, 8), (4, 6, 14), (1, 3, 5) and (6, 9…
- Annual demand is 24,000 units over 300 working days (80 per day), ordering/setup cost ₹400, holding cost ₹10 per unit per year, and the…
- A machine is scheduled for 480 minutes. It stops for 48 minutes, has an ideal cycle time of 0.5 minute per unit, makes 800 units in total…
- A process has mean 50.4 and standard deviation 0.5, with specification limits of 49.0 and 52.5. The Cpk is closest to
- A p-chart monitors a process with an average fraction defective of 0.04 using samples of 200. The 3-sigma control limits are