Management & CommerceVery hardMBA Placement · Operations · Analytics
Project network: A (4 days) and B (6) start together; C (5) follows A; D (3) follows B; E (4) follows both C and D. Crash limits and cost per day: A 1 day at ₹80, B 2 days at ₹60, C 1 day at ₹90, D 1 day at ₹70, E 1 day at ₹100. The minimum cost to cut the project duration by 3 days is
- A. ₹300
- B. ₹390
- C. ₹240
- D. ₹420
Correct answer: B. ₹390
Both paths (A-C-E and B-D-E) are 13 days. Day 1: crash E (₹100). Day 2: crash A and B (₹140). Day 3: crash C and B again (₹150). Total ₹390, found as the cheapest cut across both critical paths at each step.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A project has four sequential activities with (optimistic, most likely, pessimistic) times of (2, 5, 8), (4, 6, 14), (1, 3, 5) and (6, 9…
- Annual demand is 24,000 units over 300 working days (80 per day), ordering/setup cost ₹400, holding cost ₹10 per unit per year, and the…
- A machine is scheduled for 480 minutes. It stops for 48 minutes, has an ideal cycle time of 0.5 minute per unit, makes 800 units in total…
- A process has mean 50.4 and standard deviation 0.5, with specification limits of 49.0 and 52.5. The Cpk is closest to
- A p-chart monitors a process with an average fraction defective of 0.04 using samples of 200. The 3-sigma control limits are
- A service centre has on average 12 customers in the system (waiting plus being served), customers arrive at 4 per minute and the average…