Project network: A (4 days) and B (6) start together; C (5) follows A; D (3) follows B; E (4) follows both C and D. Crash limits and cost per day: A 1 day at ₹80, B 2 days at ₹60, C 1 day at ₹90, D 1 day at ₹70, E 1 day at ₹100. The minimum cost to cut the project duration by 3 days is

  1. A. ₹300
  2. B. ₹390
  3. C. ₹240
  4. D. ₹420

Correct answer: B. ₹390

Both paths (A-C-E and B-D-E) are 13 days. Day 1: crash E (₹100). Day 2: crash A and B (₹140). Day 3: crash C and B again (₹150). Total ₹390, found as the cheapest cut across both critical paths at each step.