A project has four sequential activities with (optimistic, most likely, pessimistic) times of (2, 5, 8), (4, 6, 14), (1, 3, 5) and (6, 9, 12) days. Using PERT, the probability of finishing within 26 days is closest to
- A. 80.9%
- B. 69.1%
- C. 64.9%
- D. 84.1%
Correct answer: A. 80.9%
Expected times are 5, 7, 3 and 9 (total 24) with variances 1, 2.78, 0.44 and 1, total 5.22, σ = 2.285. z = (26 − 24)/2.285 = 0.875, giving 80.9%. Using the variance as if it were σ gives 64.9%.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Annual demand is 24,000 units over 300 working days (80 per day), ordering/setup cost ₹400, holding cost ₹10 per unit per year, and the…
- A machine is scheduled for 480 minutes. It stops for 48 minutes, has an ideal cycle time of 0.5 minute per unit, makes 800 units in total…
- A process has mean 50.4 and standard deviation 0.5, with specification limits of 49.0 and 52.5. The Cpk is closest to
- A p-chart monitors a process with an average fraction defective of 0.04 using samples of 200. The 3-sigma control limits are
- A service centre has on average 12 customers in the system (waiting plus being served), customers arrive at 4 per minute and the average…
- Prior probabilities of two market states are 0.4 and 0.6. Payoffs: Alternative A gives 100 and 20; B gives 60 and 60; C gives 10 and 150…