A project has four sequential activities with (optimistic, most likely, pessimistic) times of (2, 5, 8), (4, 6, 14), (1, 3, 5) and (6, 9, 12) days. Using PERT, the probability of finishing within 26 days is closest to

  1. A. 80.9%
  2. B. 69.1%
  3. C. 64.9%
  4. D. 84.1%

Correct answer: A. 80.9%

Expected times are 5, 7, 3 and 9 (total 24) with variances 1, 2.78, 0.44 and 1, total 5.22, σ = 2.285. z = (26 − 24)/2.285 = 0.875, giving 80.9%. Using the variance as if it were σ gives 64.9%.