Management & CommerceHardMBA Placement · Operations · Analytics
Four jobs must be assigned to four machines, one each. The cost matrix (rows jobs 1-4, columns machines 1-4) is: job 1: 14, 9, 17, 12; job 2: 11, 15, 10, 16; job 3: 13, 12, 9, 14; job 4: 18, 11, 15, 10. The minimum total cost is
- A. 41
- B. 39
- C. 36
- D. 44
Correct answer: B. 39
The optimal assignment is job 1 to machine 2 (9), job 2 to machine 1 (11), job 3 to machine 3 (9) and job 4 to machine 4 (10): 39. Greedily choosing each row's minimum fails because job 2 and job 3 would clash.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Demand forecast errors (actual − forecast) over five periods are +5, −3, +6, +8 and +4. The tracking signal after five periods is closest to
- Project network: A (4 days) and B (6) start together; C (5) follows A; D (3) follows B; E (4) follows both C and D. Crash limits and cost…
- A project has four sequential activities with (optimistic, most likely, pessimistic) times of (2, 5, 8), (4, 6, 14), (1, 3, 5) and (6, 9…
- Annual demand is 24,000 units over 300 working days (80 per day), ordering/setup cost ₹400, holding cost ₹10 per unit per year, and the…
- A machine is scheduled for 480 minutes. It stops for 48 minutes, has an ideal cycle time of 0.5 minute per unit, makes 800 units in total…
- A process has mean 50.4 and standard deviation 0.5, with specification limits of 49.0 and 52.5. The Cpk is closest to