Daily demand averages 100 units with a standard deviation of 20; the lead time averages 9 days with a standard deviation of 2 days (independent of demand). For a 95% service level (z = 1.645), the reorder point is closest to:

  1. A. 999 units
  2. B. 1,229 units
  3. C. 1,243 units
  4. D. 1,328 units

Correct answer: C. 1,243 units

Standard deviation of lead-time demand = √(L·σd² + d²·σL²) = √(9 × 400 + 10,000 × 4) = 208.8. Safety stock = 1.645 × 208.8 ≈ 343, so ROP = 900 + 343 = 1,243. Ignoring lead-time variability gives 999, ignoring demand variability gives 1,229, and adding the two standard deviations directly gives 1,328.