Management & CommerceVery hardMBA Placement · Operations · Analytics
Daily demand has mean 100 and standard deviation 20. The supplier's lead time has mean 9 days and standard deviation 2 days (independent of demand). For a 95% cycle service level (z = 1.645), the safety stock is closest to
- A. 99 units
- B. 343 units
- C. 329 units
- D. 428 units
Correct answer: B. 343 units
σ over lead time = √(9 × 20² + 100² × 2²) = √(3,600 + 40,000) = 208.8. Safety stock = 1.645 × 208.8 = 343. Ignoring lead-time variability gives 99 and ignoring demand variability gives 329.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- Customers arrive at 8 per hour (Poisson) at a service desk with two servers, each serving at 5 customers per hour (exponential). The…
- A line must produce 480 units in an 8-hour shift. The total work content of all tasks is 5.4 minutes per unit. With perfect balancing, the…
- A firm maximises 40x + 30y subject to machine hours 2x + y ≤ 100, labour hours x + y ≤ 80 and x ≤ 40. At the optimum, the shadow price…
- Four jobs must be assigned to four machines, one each. The cost matrix (rows jobs 1-4, columns machines 1-4) is: job 1: 14, 9, 17, 12; job…
- Demand forecast errors (actual − forecast) over five periods are +5, −3, +6, +8 and +4. The tracking signal after five periods is closest to
- Project network: A (4 days) and B (6) start together; C (5) follows A; D (3) follows B; E (4) follows both C and D. Crash limits and cost…