A project's critical path has three activities with (optimistic, most likely, pessimistic) durations in days: (6, 9, 12), (4, 10, 16) and (10, 13, 22). Given Phi(1) = 0.841, Phi(0.5) = 0.691, Phi(0.33) = 0.629 and Phi(2) = 0.977, what is the probability of completing within 36 days?
- A. 84.1%
- B. 62.9%
- C. 69.1%
- D. 97.7%
Correct answer: A. 84.1%
Expected durations 9, 10 and 14 give 33 days; variances ((b - a)/6)^2 = 1, 4 and 4 sum to 9, so sigma = 3 and z = (36 - 33)/3 = 1, giving 84.1%. Using the variance 9 as sigma gives 62.9%.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- A process has mean 50, standard deviation 2, USL 56 and LSL 40. What is its Cpk?
- Maximise 40x + 30y subject to x + y <= 12 (labour hours), 2x + y <= 16 (machine hours), x, y >= 0. What is the shadow price per extra…
- Annual demand is 12,000 units, ordering cost is ₹300 per order and holding cost is 20% of the unit price per year. The supplier charges…
- Customers arrive at a service counter at 8 per hour (Poisson) and are served at 10 per hour (exponential), a single-server M/M/1 queue…
- A firm maximises profit 40x + 30y subject to 2x + y ≤ 100 (machine hours), x + y ≤ 80 (labour hours) and x ≤ 40. At the optimum, the…
- A forecaster uses simple exponential smoothing with α = 0.3 and an initial forecast of 100 for period 1. The actual demands in periods 1…