A project's critical path has three activities with (optimistic, most likely, pessimistic) durations in days: (6, 9, 12), (4, 10, 16) and (10, 13, 22). Given Phi(1) = 0.841, Phi(0.5) = 0.691, Phi(0.33) = 0.629 and Phi(2) = 0.977, what is the probability of completing within 36 days?

  1. A. 84.1%
  2. B. 62.9%
  3. C. 69.1%
  4. D. 97.7%

Correct answer: A. 84.1%

Expected durations 9, 10 and 14 give 33 days; variances ((b - a)/6)^2 = 1, 4 and 4 sum to 9, so sigma = 3 and z = (36 - 33)/3 = 1, giving 84.1%. Using the variance 9 as sigma gives 62.9%.