An item has a gross requirement of 200 units in week 6, with 50 on hand, no scheduled receipts, a lead time of 2 weeks, and a lot size that must be a multiple of 100. The planned order release is
- A. 150 units in week 4
- B. 200 units in week 6
- C. 200 units in week 4
- D. 200 units in week 2
Correct answer: C. 200 units in week 4
Net requirement = 200 − 50 = 150. Orders must be in multiples of 100, so 200 units. They must arrive in week 6, so release 2 weeks earlier, in week 4.
Practise more Operations, Supply Chain & Business Analytics questionsOperations, Supply Chain & Business Analytics: notes and key points
More Operations, Supply Chain & Business Analytics questions
- The first unit of a job takes 100 hours and the cumulative average time follows an 80% learning curve. Total hours for units 5 to 8…
- A regression with n = 30 observations and k = 4 predictors has R² = 0.80. The adjusted R² is
- A service has two servers, each serving 20 customers an hour (M/M/2), and arrivals of 30 an hour. The average number of customers waiting…
- A project has two activities in sequence on the critical path: A takes 8 days (can be cut by 3 days at ₹400 a day) and B takes 6 days (can…
- Machine A makes 60% of items with a 2% defect rate; machine B makes 40% with a 5% defect rate. An item chosen at random is defective. The…
- Two warehouses each face independent weekly demand with a standard deviation of 30 and the same lead time and service level. If they are…