A, B and C can do a job alone in 15, 30 and 10 days respectively. In how many days will they finish it working together?
- A. 18.33 days
- B. 10 days
- C. 6 days
- D. 5 days
Correct answer: D. 5 days
Combined rate = 1/15 + 1/30 + 1/10 = 0.2 ≈ 1/5 per day, so they need 5 days.
More Time and Work questions
- 4 men working 8 hours a day can finish a job in 20 days. If they work only 5 hours a day, how many days will they take?
- Priya can complete a job in 45 days and Neha alone can complete it in 90 days. In how many days will they finish it together?
- Priya can complete a job in 24 days and Manoj alone can complete it in 8 days. In how many days will they finish it together?
- 6 workers can build a wall in 10 days. How many days will 30 workers (working at the same rate) take?
- A and B together can do a job in 10 days. A alone can do it in 15 days. How long will B alone take?
- A pipe can fill a tank in 10 hours and an outlet can empty the full tank in 15 hours. If both are opened together on an empty tank, how…