A, B and C can do a job alone in 15, 30 and 10 days respectively. In how many days will they finish it working together?

  1. A. 18.33 days
  2. B. 10 days
  3. C. 6 days
  4. D. 5 days

Correct answer: D. 5 days

Combined rate = 1/15 + 1/30 + 1/10 = 0.2 ≈ 1/5 per day, so they need 5 days.