Quantitative AptitudeModerateSSC CGL · RRB NTPC · IBPS

4 men working 8 hours a day can finish a job in 20 days. If they work only 5 hours a day, how many days will they take?

  1. A. 32 days
  2. B. 23 days
  3. C. 35 days
  4. D. 12.5 days

Correct answer: A. 32 days

Total work = 4 × 8 × 20 = 640 man-hours. At 5 hours a day, days = 640/(4 × 5) = 32.