Quantitative AptitudeHardIBPS Clerk · SBI Clerk
The efficiencies of A and B are in the ratio 4:1. Together they complete a job in 8 days. How many days will B alone take?
- A. 10 days
- B. 40 days
- C. 16 days
- D. 43 days
Correct answer: B. 40 days
Efficiency ratio A:B = 4:1. Total work = 8 × (4 + 1) = 40 units. B alone = 40 ÷ 1 = 40 days.
हिंदी में
A और B की कार्यक्षमता का अनुपात 4:1 है। साथ मिलकर वे एक कार्य 8 दिन में पूरा करते हैं। B अकेला कितने दिन लेगा?
- A. 10 days
- B. 40 days
- C. 16 days
- D. 43 days
उत्तर: B. कार्यक्षमता अनुपात A:B = 4:1। कुल कार्य = 8 × (4 + 1) = 40 इकाई। B अकेला = 40 ÷ 1 = 40 दिन।
More Time and Work questions
- A, B and C can complete a work alone in 6, 10 and 15 days respectively. They work together and are paid ₹2,400 in all, each in proportion…
- A can complete a piece of work in 12 days and B in 20 days. They work together for 3 days, after which A leaves. B alone will finish the…
- The efficiencies of A and B are in the ratio 5:3. Together they complete a job in 6 days. How many days will B alone take?
- 40 men can complete a work in 36 days. After 12 days, 60 more men join them. In how many more days will the remaining work be completed?
- A tap fills a tank in 6 hours. Because of a leak at the bottom, it takes 12 hours to fill the tank. The leak alone can empty the full tank…
- 60 men can complete a work in 30 days. After 4 days, 15 more men join them. In how many more days will the remaining work be completed?