Quantitative AptitudeVery hardIBPS PO Mains · SBI PO Mains
20 men can complete a work in 30 days. After 10 days, 30 more men join them. In how many more days will the remaining work be completed?
- A. 6.5 days
- B. 20 days
- C. 8 days
- D. 10 days
Correct answer: C. 8 days
Remaining work = 20 men × 20 days = 400 man-days. With 50 men: 400 ÷ 50 = 8 days.
हिंदी में
20 आदमी किसी कार्य को 30 दिन में पूरा कर सकते हैं। 10 दिन बाद 30 आदमी और जुड़ जाते हैं। शेष कार्य कितने और दिनों में पूरा होगा?
- A. 6.5 days
- B. 20 days
- C. 8 days
- D. 10 days
उत्तर: C. शेष कार्य = 20 आदमी × 20 दिन = 400 आदमी-दिन। 50 आदमियों के साथ: 400 ÷ 50 = 8 दिन।
More Time and Work questions
- A can complete a piece of work in 15 days and B in 15 days. They work together for 3 days, after which A leaves. B alone will finish the…
- The efficiencies of A and B are in the ratio 2:1. Together they complete a job in 18 days. How many days will B alone take?
- 20 men can complete a work in 30 days. After 6 days, 20 more men join them. In how many more days will the remaining work be completed?
- A, B and C can complete a work alone in 10, 12 and 24 days respectively. They work together and are paid ₹4,500 in all, each in proportion…
- A can complete a piece of work in 24 days and B in 15 days. They work together for 4 days, after which A leaves. B alone will finish the…
- A tap fills a tank in 12 hours. Because of a leak at the bottom, it takes 16 hours to fill the tank. The leak alone can empty the full…