Quantitative AptitudeHardIBPS Clerk · SBI Clerk
The efficiencies of A and B are in the ratio 3:1. Together they complete a job in 15 days. How many days will B alone take?
- A. 60 days
- B. 20 days
- C. 45 days
- D. 30 days
Correct answer: A. 60 days
Efficiency ratio A:B = 3:1. Total work = 15 × (3 + 1) = 60 units. B alone = 60 ÷ 1 = 60 days.
हिंदी में
A और B की कार्यक्षमता का अनुपात 3:1 है। साथ मिलकर वे एक कार्य 15 दिन में पूरा करते हैं। B अकेला कितने दिन लेगा?
- A. 60 days
- B. 20 days
- C. 45 days
- D. 30 days
उत्तर: A. कार्यक्षमता अनुपात A:B = 3:1। कुल कार्य = 15 × (3 + 1) = 60 इकाई। B अकेला = 60 ÷ 1 = 60 दिन।
More Time and Work questions
- Pipes A and B can fill a tank in 20 hours and 40 hours respectively, while an outlet C can empty the full tank in 30 hours. If all three…
- A can complete a piece of work in 30 days and B in 36 days. They work together for 6 days, after which A leaves. B alone will finish the…
- 40 men can complete a work in 45 days. After 5 days, 60 more men join them. In how many more days will the remaining work be completed?
- A can complete a piece of work in 12 days and B in 15 days. They work together for 2 days, after which A leaves. B alone will finish the…
- The efficiencies of A and B are in the ratio 2:1. Together they complete a job in 6 days. How many days will B alone take?
- 20 men can complete a work in 24 days. After 6 days, 10 more men join them. In how many more days will the remaining work be completed?