45 men can complete a work in 20 days. After 12 days, 15 more men join them. In how many more days will the remaining work be completed?
- A. 4.5 days
- B. 8 days
- C. 24 days
- D. 6 days
Correct answer: D. 6 days
Remaining work = 45 men × 8 days = 360 man-days. With 60 men: 360 ÷ 60 = 6 days.
हिंदी में
45 आदमी किसी कार्य को 20 दिन में पूरा कर सकते हैं। 12 दिन बाद 15 आदमी और जुड़ जाते हैं। शेष कार्य कितने और दिनों में पूरा होगा?
- A. 4.5 days
- B. 8 days
- C. 24 days
- D. 6 days
उत्तर: D. शेष कार्य = 45 आदमी × 8 दिन = 360 आदमी-दिन। 60 आदमियों के साथ: 360 ÷ 60 = 6 दिन।
More Time and Work questions
- A and B can complete a work in 20 days and 30 days respectively. They work on alternate days, beginning with A. The work will be completed…
- A, B and C can complete a work alone in 12, 24 and 12 days respectively. They work together and are paid ₹6,000 in all, each in proportion…
- A tap fills a tank in 6 hours. Because of a leak at the bottom, it takes 18 hours to fill the tank. The leak alone can empty the full tank…
- A can complete a piece of work in 20 days and B in 30 days. They work together for 6 days, after which A leaves. B alone will finish the…
- The efficiencies of A and B are in the ratio 3:2. Together they complete a job in 12 days. How many days will B alone take?
- 45 men can complete a work in 30 days. After 8 days, 15 more men join them. In how many more days will the remaining work be completed?