Quantitative AptitudeHardIBPS Clerk · SBI Clerk
The efficiencies of A and B are in the ratio 3:2. Together they complete a job in 12 days. How many days will B alone take?
- A. 24 days
- B. 30 days
- C. 33 days
- D. 18 days
Correct answer: B. 30 days
Efficiency ratio A:B = 3:2. Total work = 12 × (3 + 2) = 60 units. B alone = 60 ÷ 2 = 30 days.
हिंदी में
A और B की कार्यक्षमता का अनुपात 3:2 है। साथ मिलकर वे एक कार्य 12 दिन में पूरा करते हैं। B अकेला कितने दिन लेगा?
- A. 24 days
- B. 30 days
- C. 33 days
- D. 18 days
उत्तर: B. कार्यक्षमता अनुपात A:B = 3:2। कुल कार्य = 12 × (3 + 2) = 60 इकाई। B अकेला = 60 ÷ 2 = 30 दिन।
More Time and Work questions
- 45 men can complete a work in 30 days. After 8 days, 15 more men join them. In how many more days will the remaining work be completed?
- A can complete a piece of work in 24 days and B in 36 days. They work together for 3 days, after which A leaves. B alone will finish the…
- A can complete a piece of work in 20 days and B in 36 days. They work together for 2 days, after which A leaves. B alone will finish the…
- 45 men can complete a work in 36 days. After 12 days, 30 more men join them. In how many more days will the remaining work be completed?
- A can complete a piece of work in 20 days and B in 60 days. They work together for 2 days, after which A leaves. B alone will finish the…
- The efficiencies of A and B are in the ratio 3:1. Together they complete a job in 12 days. How many days will B alone take?