Quantitative AptitudeEasySSC CHSL · RRB Group D
The efficiencies of A and B are in the ratio 3 : 2. If B takes 30 days to finish a job, how long will A take?
- A. 20 days
- B. 45 days
- C. 25 days
- D. 18 days
Correct answer: A. 20 days
Time is inversely proportional to efficiency: A's time = 30 × 2/3 = 20 days.
हिंदी में
A और B की कार्यक्षमताओं का अनुपात 3 : 2 है। यदि B किसी कार्य को 30 दिन में पूरा करता है, तो A कितना समय लेगा?
- A. 20 दिन
- B. 45 दिन
- C. 25 दिन
- D. 18 दिन
उत्तर: A. समय कार्यक्षमता के व्युत्क्रमानुपाती होता है: A का समय = 30 × 2/3 = 20 दिन।
More Time and Work questions
- A completes 25% of a job in 5 days and B completes 20% of it in 6 days. How long will they take to finish the job together?
- A, B and C can do a job alone in 12, 16 and 24 days. How long will they take working together?
- A and B together can do a job in 8 days, and A alone in 12 days. B works alone for 3 days and then A finishes the rest. How many days does…
- 4 men or 6 women can do a job in 15 days. How long will 2 men and 3 women take?
- If 5 painters paint 5 rooms in 5 days, how many days will 10 painters take to paint 10 rooms?
- A does 40% of a job in 8 days, and B finishes the remaining work in 6 days. How long would they take to do the whole job together?