Quantitative AptitudeModerateSSC CHSL · SSC CGL
A, B and C can do a job alone in 12, 16 and 24 days. How long will they take working together?
- A. 6 days
- B. 52/3 days
- C. 16/3 days
- D. 5 days
Correct answer: C. 16/3 days
Work = 48 units: A 4, B 3, C 2 per day, total 9. Time = 48/9 = 16/3 days (5⅓ days).
हिंदी में
A, B और C किसी कार्य को अकेले क्रमशः 12, 16 और 24 दिन में कर सकते हैं। साथ काम करने पर वे कितना समय लेंगे?
- A. 6 दिन
- B. 52/3 दिन
- C. 16/3 दिन
- D. 5 दिन
उत्तर: C. कार्य = 48 इकाई: A प्रतिदिन 4, B 3, C 2, कुल 9। समय = 48/9 = 16/3 दिन (5⅓ दिन)।
More Time and Work questions
- A and B together can do a job in 8 days, and A alone in 12 days. B works alone for 3 days and then A finishes the rest. How many days does…
- 4 men or 6 women can do a job in 15 days. How long will 2 men and 3 women take?
- If 5 painters paint 5 rooms in 5 days, how many days will 10 painters take to paint 10 rooms?
- A does 40% of a job in 8 days, and B finishes the remaining work in 6 days. How long would they take to do the whole job together?
- Working 6 hours a day, a man finishes a job in 10 days. In how many days will he finish it working 7.5 hours a day?
- 12 carpenters working 8 hours a day make 360 chairs in 15 days. How many days will 16 carpenters working 9 hours a day take to make 540…