CS FundamentalsVery hardProduct company interview · GATE level
Basic COCOMO for a semi-detached project uses Effort = 3.0 x KLOC^1.12 person-months and Development time = 2.5 x Effort^0.35 months. For a 50 KLOC project, what are the effort, the development time and the average staffing?
- A. About 240 PM, 17.0 months, 14.1 people
- B. About 150 PM, 14.4 months, 10.4 people
- C. About 240 PM, 14.1 months, 17.0 people
- D. About 240 PM, 24.0 months, 10.0 people
Correct answer: A. About 240 PM, 17.0 months, 14.1 people
Effort = 3.0 x 50^1.12. 50^1.12 = e^(1.12 x ln 50) = e^(4.381) = about 79.9, so effort is about 240 person-months. Time = 2.5 x 240^0.35 = 2.5 x 6.81 = about 17.0 months. Average staff = effort / time = 240/17.0 = about 14.1 people. 150 PM ignores the exponent (3.0 x 50); 14.1 months and 17.0 people swaps the schedule and the staffing; 24 months assumes 10 people. Because time grows only as effort^0.35, doubling the size does not double the schedule.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Intermediate COCOMO for an organic project uses Effort = 3.2 x KLOC^1.05 x EAF, where EAF is the product of the cost-driver multipliers. A…
- Function point counts with weights in brackets: external inputs - 6 simple (3), 4 average (4), 2 complex (6); external outputs - 5 average…
- A system is estimated at 300 function points, and the chosen language averages 53 lines of code per function point. Using basic COCOMO for…
- A program has 12 distinct operators, 20 distinct operands, 90 total operator occurrences and 70 total operand occurrences. Using…
- Activities (duration in days; predecessors): A (4; -), B (6; -), C (3; A), D (5; A), E (4; B, C), F (7; B), G (3; D, E), H (2; F, G), I…
- Activities (duration in days; predecessors): A (3; -), B (5; A), C (4; A), D (2; C), E (6; B), F (5; C), G (4; B, D), H (3; E, F, G). How…