A sprint commitment had stories of 8, 5, 5, 3 and 3 points. At the sprint's end the 8, one 5 and both 3s meet the Definition of Done; the other 5-point story is 90% done. What velocity should the team record?

  1. A. 19
  2. B. 23.5
  3. C. 24
  4. D. 14

Correct answer: A. 19

Only done stories count: 8 + 5 + 3 + 3 = 19. Partial credit (4.5 points) would give 23.5 and overstate capacity; the unfinished story is re-estimated if needed and returns to the backlog.