CS FundamentalsHardProduct-company placement · Kanban interview
On a cumulative flow diagram for a Kanban board, the band for 'In Review' keeps getting wider over several weeks while the 'Done' line rises slowly. What does this indicate?
- A. Review is a bottleneck: work is arriving faster than it leaves review, so WIP and lead time are growing
- B. Throughput is increasing
- C. The team is finishing work faster
- D. Nothing; band widths have no meaning
Correct answer: A. Review is a bottleneck: work is arriving faster than it leaves review, so WIP and lead time are growing
Band width at a point in time is the WIP in that state; a widening band means arrivals exceed departures. By Little's law, growing WIP at steady throughput means longer lead times.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A customer requests a feature on 1 March; the team starts work on it on 10 March and delivers it on 15 March. Using common Kanban…
- According to the 2020 Scrum Guide, how many of these are true? 1. An Increment may be delivered to stakeholders before the end of the…
- A fragment contains total = 0 immediately followed by total = compute(), with no use of total in between, and later print(rate) where rate…
- In domain testing for integer inputs, a program accepts points satisfying x + y ≤ 10 (a closed boundary). Which pair of test points is the…
- A task has optimistic 4 days, most likely 6 days and pessimistic 20 days. What are the triangular-distribution mean (a + m + b)/3 and the…
- In IFPUG function-point counting, which of these is an external output (EO) rather than an external inquiry (EQ)?