CS FundamentalsModerateGATE CS · Infosys
Using basic COCOMO in the organic mode (effort = 2.4 × (KLOC)^1.05 person-months), the effort for a 50 KLOC product is closest to:
- A. 146 person-months
- B. 240 person-months
- C. 394 person-months
- D. 120 person-months
Correct answer: A. 146 person-months
2.4 × 50^1.05 = 2.4 × 60.8 ≈ 146 person-months. 240 and 394 are the semi-detached (3.0 × KLOC^1.12) and embedded (3.6 × KLOC^1.20) values, and 120 wrongly treats effort as linear in size.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A program consists of a main routine and one procedure. Their flow graphs are drawn as two separate connected components with a total of E…
- Three sequential activities lie on the critical path of a project. Their (optimistic, most likely, pessimistic) durations in days are A…
- A server unit has MTTF = 400 hours and MTTR = 100 hours. Two such units fail and are repaired independently, and the service stays up if…
- A product passes through three defect-removal activities that independently catch 60%, 70% and 50% of the defects present when they run…
- Module A passes an entire customer record (a composite structure) to module B, but B uses only the customer ID field. This is an example of:
- In function point analysis the weights (simple, average, complex) are: external inputs 3, 4, 6; external outputs 4, 5, 7; external…