CS FundamentalsHardGATE CS · TCS NQT

A product passes through three defect-removal activities that independently catch 60%, 70% and 50% of the defects present when they run. The overall defect removal efficiency after all three is:

  1. A. 60%
  2. B. 94%
  3. C. 80%
  4. D. 87%

Correct answer: B. 94%

Defects surviving each stage multiply: 0.4 × 0.3 × 0.5 = 0.06, so 94% are removed. Averaging the three figures (60%) or adding them (capped at 100%) are the usual errors.