CS FundamentalsHardGATE CS · Software Engineering · Advanced
In function point analysis the weights (simple, average, complex) are: external inputs 3, 4, 6; external outputs 4, 5, 7; external inquiries 3, 4, 6; internal logical files 7, 10, 15; external interface files 5, 7, 10. A system has EI: 6 simple, 10 average, 4 complex; EO: 5 simple, 6 average, 3 complex; EQ: 4 simple, 4 average, 2 complex; ILF: 3 simple, 4 average, 1 complex; EIF: 2 simple, 2 average, 1 complex. The 14 general system characteristics are rated 0-5: eight are rated 3, four are rated 4 and two are rated 1. The value adjustment factor is 0.65 + 0.01 x (sum of ratings). What is the adjusted function point count, to the nearest whole number?
- A. 282
- B. 324
- C. 345
- D. 303
Correct answer: B. 324
Unadjusted count = 303. The ratings sum to 42, so VAF = 1.07 and the adjusted count is 303 x 1.07 = 324.2, i.e. 324. Using the raw UFP, or a VAF built from a shifted rating scale, gives the wrong totals.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- Basic COCOMO for an embedded-mode project uses effort E = 3.6 (KLOC)^1.20 person-months and development time D = 2.5 E^0.32 months. For a…
- A program has 14 distinct operators, 22 distinct operands, 82 operator occurrences and 61 operand occurrences. Using Halstead's measures…
- The control-flow graphs of a program's two separate routines have E = 16, N = 13 and E = 9, N = 8 edges and nodes respectively (each graph…
- A project has these activities (duration in days; predecessors): A (3; none), B (4; none), C (5; A), D (2; A, B), E (6; B), F (4; C, D), G…
- The critical path of a project has four activities with (optimistic, most likely, pessimistic) durations in days: (2, 4, 8), (3, 5, 13)…
- A system has component A (reliability 0.98) in series with a parallel pair B (0.90) and C (0.85) - the pair works if at least one works…