CS FundamentalsVery hardGATE CS · MBA project management
Three sequential activities lie on the critical path of a project. Their (optimistic, most likely, pessimistic) durations in days are A (2, 4, 12), B (3, 6, 9) and C (4, 7, 16). Under PERT assumptions (beta distribution, normal approximation for the total), the probability of finishing within 22 days is about:
- A. 74%
- B. 65%
- C. 86%
- D. 93%
Correct answer: C. 86%
Expected times are 5, 6 and 8, so the mean is 19 days. Variances ((P − O)/6)² sum to 2.78 + 1 + 4 = 7.78, so σ = 2.79 and z = (22 − 19)/2.79 = 1.08, giving about 86%. Adding standard deviations instead of variances gives the 74% trap.
Practise more Software Engineering, Git and Cloud Basics questionsSoftware Engineering, Git and Cloud Basics: notes and key points
More Software Engineering, Git and Cloud Basics questions
- A server unit has MTTF = 400 hours and MTTR = 100 hours. Two such units fail and are repaired independently, and the service stays up if…
- A product passes through three defect-removal activities that independently catch 60%, 70% and 50% of the defects present when they run…
- Module A passes an entire customer record (a composite structure) to module B, but B uses only the customer ID field. This is an example of:
- In function point analysis the weights (simple, average, complex) are: external inputs 3, 4, 6; external outputs 4, 5, 7; external…
- Basic COCOMO for an embedded-mode project uses effort E = 3.6 (KLOC)^1.20 person-months and development time D = 2.5 E^0.32 months. For a…
- A program has 14 distinct operators, 22 distinct operands, 82 operator occurrences and 61 operand occurrences. Using Halstead's measures…