Three sequential activities lie on the critical path of a project. Their (optimistic, most likely, pessimistic) durations in days are A (2, 4, 12), B (3, 6, 9) and C (4, 7, 16). Under PERT assumptions (beta distribution, normal approximation for the total), the probability of finishing within 22 days is about:

  1. A. 74%
  2. B. 65%
  3. C. 86%
  4. D. 93%

Correct answer: C. 86%

Expected times are 5, 6 and 8, so the mean is 19 days. Variances ((P − O)/6)² sum to 2.78 + 1 + 4 = 7.78, so σ = 2.79 and z = (22 − 19)/2.79 = 1.08, giving about 86%. Adding standard deviations instead of variances gives the 74% trap.