Mechanical EngineeringHard
In standard CNC part programming, the preparatory code G02 commands
- A. linear interpolation
- B. clockwise circular interpolation
- C. counter-clockwise circular interpolation
- D. rapid traverse
Correct answer: B. clockwise circular interpolation
G00 is rapid traverse, G01 linear, G02 clockwise arc and G03 counter-clockwise arc.
Practise more Manufacturing, Materials & Industrial Engineering (ISRO Mech) questionsManufacturing, Materials & Industrial Engineering (ISRO Mech): notes and key points
More Manufacturing, Materials & Industrial Engineering (ISRO Mech) questions
- An X-bar control chart is based on samples of size 4 from a process with mean 50 and standard deviation 2. The upper 3-sigma control limit…
- Annual demand is 1000 units, ordering cost is Rs 50 per order and holding cost is Rs 10 per unit per year. The economic order quantity is
- A PERT activity has optimistic time 2, most likely time 5 and pessimistic time 14. Its expected time is
- In simple exponential smoothing with alpha = 0.2, the previous forecast is 100 and the actual demand is 120. The new forecast is
- A unity-feedback system with G(s) = K/(s(s + 2)) is required to have a damping ratio of 0.5. The gain K must be
- On a Bode magnitude plot, a double pole at the origin contributes a slope of